Takt time (min/unit) 2
Takt time (s/unit) 120

Formula: takt = available time ÷ demand

Step-by-step with your numbers:
1. Values used:
2. Available time = 480
3. Customer demand = 240 units
4.
5. Takt time = Available time / Customer demand = 480 / 240 = 2min/unit
6. Takt time = 120s/unit
Did we solve your problem today?

Takt time is the rhythm production must hit to satisfy demand.

The math behind it

takt time = available production time ÷ customer demand (units).

Worked example

480 min ÷ 240 units → 2 min/unit.